Power Analysis Of Different Distribution Systems

Distribution Systems

1. SINGLE LINE DIAGRAM OF MICROGRID IEEE TEST SYSTEM :

Characteristic Features:

  • Microgrid consists of two parts:
  • Solid State Circuit Breakers
  • Micro-power supplies (distributed generations)
  • Sub-station transformer
  • Seven interconnected buses (bus1 is generator bus; buses 5,6,7 are load buses)
  • Three PMT’s
  • Three breakers

The reason behind the selection of SLD:

Due to the rapid growth of electricity demand, grid expansion, and several worldwide blackouts, the vulnerability of large power grids is fully exposed. Therefore the world has now trying to move towards a new power technology-Distributed Generation i-e DG through microgrids. Distributed power generation has outstanding features.

Advantages:

  • flexible power generation
  • Environmental compatibility
  • Better controllability of power system operation
  • Better meet with the power quality
  • Increased reliability of consumers

Feasibility:

 Microgrids can be installed in a limited area and their results can be studied. Thus it’s feasible to implement this on a limited scale first then move towards a larger scale.

Cost Analysis:

Additional investment is required in this innovative technique.

Cost to benefit ratio must be calculated before installation.

2. SINGLE-LINE DIAGRAM OF TEST POWER SYSTEM:

 Fig.2   Sld of a general power system to study different power system parameters

Characteristic Features:

·         3-sync.generators                   9-bus system                         6 lines

·         3 loads                                    3- two winding t/f

Reasons behind the selection of SLD:

This SLD enables the power engineer to have a deep eye on the following aspects:-

·         Analyze the dynamic performance of interconnected power systems.

·         Examines the characteristics of the various components of a power system during normal operating conditions and during disturbances.

·          Explores the detailed mathematical models of system components and analyzes the system behavior using the necessary computational tools.

Advantages:

·         Power engineers when finding out the above information then they are well able to model and operate the system in the most economical, reliable, and in an appropriate manner.

·         Besides consumers also directly benefitted.

Feasibility:

·         This SLD is very simple and easy to implement for the different areas of engineering study.

Cost Analysis:

·         Capital required for it is zero percent. It just requires determination and willpower from the Power Engineers side.

3. SINGLE LINE DIAGRAM OF SMALL DISTRIBUTION   SYSTEM:

Fig.3  Sld shows a small distribution system

Characteristic Features:

·         Above sld depicts a small distribution system. The electric company distributes power at 69kV, which in turn feeds a 13.8kV distribution system by a 13.8kV, 3-phase, 50-Hz, 20 MVA distribution transformer with an impedance of 8.5%. The 1,000kVA, 6.7% impedance transformer is used to step the voltage down from 13.8kV to 480V.

·         Here the point of the study is the understanding of harmonics generation and harmonic voltage arising due to it.

·         Keep in mind that PCC stands for “Point of common coupling”. It is the electrical connecting point or interface between the utility distribution system and the customer’s or user’s electrical distribution system.

Reasons behind the selection of SLD:

  • Improving the “power quality” is the most current topic of discussion among all the distribution Engineers of the world.
  • Until and unless the position of harmonics at each and every component of the power system is not known by the engineers then how could they improve the quality of power? Therefore the above sld is shortlisted.

Advantages:

It equipped the Distribution Engineers with the following flow advantages:-

  •  Finds the current harmonics at each and every load in the system.
  • Compare the obtained results with the IEEE Standards ratings.
  • Harmonics are filtered at each individual load and measured easily at the point PCC.
  • Feasibility:

·         Feasibility is 100%

Cost Analysis:

·         Its most economical due to PCC since no need to measure the harmonic distortion at each and every point which ultimately saves the capital

4.  SLD OF A TEST SYSTEM FOR CONTROLLING STATCOM COMPENSATION:

Characteristic Features:

 The load is grouped at bus 7 and consists of an impedance modeled as an RL load (120MW/32Mvar) supplied by a single generator (250MVA/13.8 kV) and a bulk power system modeled as an infinite bus (10GVA/230kV) by two transmission lines. The generator is powered by a multi-stage steam turbine which is connected to the network through a Y – D step-up transformer (350 MVA, 13.8/230 kV). The STATCOM/SMES i-e static synchronous compensator and superconducting magnetic energy storage system is placed at the main bus (bus 4) with the purpose of participating in the primary frequency control of the electric system together with the generator, in a case when severe disturbances have occurred.

Reasons behind the selection of this sld:

The SLD is selected since it depicts one of the fundamental concepts of power engineering which is the “primary frequency control mechanism.”A professional Engineer should, in fact, must know about the controlling of frequency and its different methods.

Advantages:

  • The knowledge of frequency, variation in frequency, and its control ultimately made the Power Engineers save the precious equipment and power system from massive damage.
  • In the meantime consumers also benefitted directly.
  • The security and reliability of the power system are enhanced.

Feasibility:

  • STATCOM /SMES is new research.
  • Requires experienced and technically sound persons to be implemented.
  • Sincere and serious efforts are required to be implemented in Pakistan.

Cost Analysis:

  •  Firstly the results can be judged by installing STATCOM/SMES at certain locations.
  • If desired results are achieved then can be implemented on large scale.
  • The cost of energy storage devices is not too high so it is economically feasible.

5. NEUTRAL GROUNDING RESISTOR:

 Fig.5  Sld depicts the protection of equipment through a grounding resistor

Characteristic Features:

  • Neutral Grounding Resistors are used to protect power transformers, power generators, and other associated equipment in your power systems against 50/60 Hz faults (short circuits) and transient phenomena (lightning).
  • Rated current: from 1 amp to 2000 A
  • Rated voltage: from 0.4 to 35kV
  • Rated Resistance: from 1 ohm to 2000 ohm
  • Rated time: 1 sec to continuous time rating
  • All Neutral Grounding Resistors are designed, rated, manufactured, and tested strictly
  • with IEEE32. Routine tests performed on each Neutral Grounding Resistor are a measurement of resistance, high voltage power frequency, insulation measurement
  • The standard unit includes the stainless steel resistor assembly plus all the required 

insulators, internal connections, and hardware installed in a standard safety enclosure. NeutralGrounding Resistor units are completely assembled, prewired, and tested at our facility

Reasons behind the selection of this sld:

  • Protection is a technique that the world engineers move to and a lot of work is still in progress for the security of the power system. That’s why the SLD has a right to be short-listed here.
  • Protection is the backbone of the power system. Due to this immense significance, this SLD is selected.
  • SLD shows in a very simple manner how can be a transformer or any equipment can be operated safely.

Advantages:

  • A little amount of initial investment protects the most precious machines.
  • Consumers have benefitted directly once again.

Feasibility:

  • The SLD shown above is much more feasible in its nature.
  • The feasibility of this can be better judged by experienced engineers at a particular location of a particular site whether they have to use this or not.

Cost Analysis:

  • Costing PKR=100,000 -10,00,000/-.
  • Professionally and technically it’s wise to invest this amount in order to save the most precious. equipment costing millions of rupees.
  • One-time initial investment saves the power system.
  • Hence security and reliability increased.

Related topic 

Leave a Comment

WhatsApp chat button